Greenfield Bridge Parkway Closure Rescheduled for Dec 9

Worker on the Greenfield Bridge, in fog (photo by Pat Hassett)
Worker on the Greenfield Bridge, in fog (photo by Pat Hassett)

17 November 2016:

WEEKEND PARKWAY EAST CLOSURE POSTPONED
BEECHWOOD BOULEVARD (GREENFIELD) BRIDGE

The City of Pittsburgh has postponed this weekend’s planned closure of the Parkway East due to the inclement weather forecasted for Saturday into Sunday. Rain possibly changing to snow along with strong winds forecasted for the site preclude the high steel work planned for this weekend.

The closure has been rescheduled for the weekend of December 9, beginning at 10:00 p.m., Friday and ending at 6:00 a.m., Monday the 12th. During this closure, Mosites and their team will finish tightening all the connections of the steel, install the deck pans over the highway, and perform miscellaneous activities.